Street Maintenance Program

  1. 2022 Reynoldsburg Street Program
  2. FUTURE STREET PROGRAMS

Street Name

Type of Improvements

Contract A

Taylor Road SW

Resurfacing, Curb Replacement, & Sidewalk

Bergenia Court

Resurfacing, Curb Replacement, & Sidewalk

Gladiolus Court

Resurfacing, Curb Replacement, & Sidewalk

Cuthbert Court

Resurfacing, Curb Replacement, & Sidewalk

Canada Court

Resurfacing & Curb Replacement

Crofton Place

Resurfacing & Curb Replacement

Crofton Circle

Resurfacing & Curb Replacement

Crofton Court

Resurfacing & Curb Replacement

Rygate Court

Resurfacing, Curb Replacement, & Sidewalk

Rygate Drive

Reconstruction, Resurfacing, Curb Replacement, & Sidewalk

Carrousel Drive E

Reconstruction, Curb Replacement, & Sidewalk

Hillridge Road

Reconstruction, Curb Replacement, & Sidewalk

COTA Bus Stop (East Main St & Oak Valley Rd)

Bus Stop Improvements

Livingston Avenue Fire Station

Full Depth Pavement Repairs & Curb Replacement

State Route 256 (from E. Main St to County line)

Full Depth Pavement Repairs, Curb Replacement, & Sidewalk

Priestly Drive (from Waggoner Rd to Quarry Park Dr)

Speed Hump Improvements

Old Highbanks Court

Resurfacing & Curb Replacement

Davidson Drive & Haft Drive Intersection

Resurfacing & Curb Replacement

JFK Park Entrance Drive

Resurfacing & Curb Replacement

Graham Road Path

Asphalt Path, Sidewalk, & Landscaping

Police Parking Lot

Reconstruction, Resurfacing, Carport, Lighting, & Landscaping

Contract B

Fallriver Drive

Asphalt Rejuvenator

Taylor Mills Drive

Asphalt Rejuvenator

Taylor Mills Place

Asphalt Rejuvenator

Linick Drive

Asphalt Rejuvenator

Bergenia Drive

Asphalt Rejuvenator

Priestly Drive

Asphalt Rejuvenator

JFK Park Main Parking Lot

Asphalt Rejuvenator

JFK Park South Parking Lot

Asphalt Rejuvenator

Livingston House Parking Lot

Asphalt Rejuvenator

Spot curb replacement will occur first and will be completed in about three weeks on each street

Resurfacing will occur several weeks after curb replacement and will take about one week to complete

Street reconstruction will take about four weeks on each street to complete, continuous curb replacement and partial driveway approach replacement will be completed the first two weeks, pavement removal and replacement will be completed in about one week, site restoration will require about one week

Sidewalk replacements will occur in the fall and will be completed in about two weeks on each street

Asphalt Rejuvenator will be completed in a single day for each street (about one hour for application and several hours to dry)